PROJECT RHEILFFORDD ERYRI
WELSH HIGHLAND RAILWAY PROJECT
2000 NEWS ARCHIVE
See also - [2009 News] [2008] [2007]
[2006] [2005] [2004]
[2003] [2002] [2001]
[2000] [1999] [1998] [1997] [1996] [1995] [1993-4]
- January 2000
- Work started on the second Phase 2 bridge contract, and the Earthwork
& Civils contract.
- A further supply of steel sleepers (and fastenings) was
shipped from Durban in South Africa.
- WHLR Ltd moved 300 tonnes of rails from Dinas to the site
near the Rhostryfan Road where Phase 2 tracklaying was to start
following completion of the trackbed works there.
- February 2000 -
The Royal Mail released its first class (26p) stamp featuring the WHR
Project, as part of the Fire and Light set of
stamps featuring projects supprted by the Millennium Commission. The
stamp features Beyer-Garratt No. 143 and train against a montage
backdrop of mountain scenery near Rhyd Ddu. The launch was marked by
the first Mail train to run on WHR (Caernarfon) and the simultaneous
launch of a 25p FR Railway Letter Service stamp featuring No. 138 (illustrated).
- The consignment of 3,000 sleepers shipped from South Africa
(see under January) arrived.
- March 2000 - Work on the first Phase 2
bridge contract was largely completed, with work on the second contract
also well advanced.
- Two ballast wagons acquired by the railway were shipped
from South Africa.
- March 18th 2000 - Blanche was
moved back to the Ffestiniog Railway by road, and replaced at Dinas by Mountaineer.
Diesel Conwy Castle was moved to Dinas on the same
day.
- March 30th 2000 - Diesel Upnor
Castle was moved by road to the Cae Wernlas Ddu construction
base, ready to become the first locomotive to work on the historic WHR
trackbed since the 1930s.
- April 17th 2000 - Agreement was reached
between representatives of the FR and WHR (Porthmadog) on the steps to
be taken to enable extension work northwards from Pen y Mount to start
later in the year. Details on the relevant route page.
- April 30th 2000 - the WHRS K1 Group made
the public launch of Project K1 2000 at Boston
Lodge and Dinas, marking the final push to complete the loco's
overhaul.
- May 5th 2000 - the pair of
self-discharging ballast wagons acquired in South Africa were delivered
to Dinas, following a consignment of South African point components
earlier the same week.
- Late May 2000 - the boiler frame of K1
was moved from Dinas to the FR.
- June 2nd/3rd 2000 - tracklaying at
Waunfawr started.
- July 20th 2000 - the last gap in the
track laid between Dinas and Waunfawr was filled.
- July 21st 2000 - HMRI carried out a
successful final inspection of Phase 2 works, leaving a "snagging list"
of tasks to be completed before opening.
- August 2nd 2000 - Garratt no. 143 was
hauled to Waunfawr "cold" between diesels Upnor Castle
and Conway Castle for checking purposes. No
problems were found. A later test saw the first coaches taken to
Waunfawr.
- August 2nd 2000 - WHR (Porthmadog)
volunteers began clearance work for surveying purposes north of Pen y
Mount.
- August 4-6th 2000 - Test trains ran to
Waunfawr for crew route familiarisation purposes outside the hours of
timetabled Caernarfon-Dinas services. Three days of testing had been
proposed by HMRI.
- August 7th 2000 - Passenger services
were extended to Waunfawr.
- September 15th 2000 - the line from
Dinas to Waunfawr was officially opened by Dafydd Wigley, Caernarfon's
MP and Member of the National Assembly for Wales.
- September 16-17th 2000 - The "Welsh
Highland Ffestival 2000" weekend saw working visits from original WHR
loco Russell, and FR Single Fairlie Taliesin.
- October 18th 2000 - Planning permission
was granted for the rock stabilisation and tunnel repair works required
at the Aberglaslyn Pass before the railway can extend into the
Snowdonia National Park.
- November 2000 - Contractors Rock
Engineering, of Porthmadog, began work at Aberglaslyn (see below). WHLR
Ltd staff and WHRS volunteers began clearance and preparation work
south of Waunfawr, while contractors Triact began their work at Betws
Garmon.
- December 4th 2000 - The restored Dinas
station building was awarded an Ian Allan National Railway Heritage
Award. S4C broadcast the documentary Ail Godi Stêm,
covering the reopening to Waunfawr.
WHR Project News page
Authored by Ben Fisher; last modified January 15th, 2004